In project management, a work breakdown structure (WBS) is an exhaustive, hierarchical (from general to specific) tree structure of deliverables and tasks that need to be performed to complete a project. The purpose of a WBS is to identify terminal elements (the actual items to be done in a project). Therefore, WBS serves as the basis for much of project planning. Work breakdown structure is a very common project management tool. Many United States government statements of work require work breakdown structures.
How to build a WBSWhether the WBS should be activity-oriented or deliverable-oriented is a subject of much discussion (http://www.maxwideman.com/musings/wbswar.htm). There are also various approaches to building the WBS for a project (see e.g. How to Build a Work Breakdown Structure below). Project management software, when used properly, can be very helpful in developing a WBS, although in early stages of WBS development, plain sticky notes are the best tool (especially in teams). An example of a work breakdown for painting a room (activity-oriented) is, to state the obvious:
The size of the WBS should generally not exceed 100-200 terminal elements (if more terminal elements seem to be required, use subprojects). The WBS should be up to 3-4 levels deep. Each level should be 5-9 elements broad. These suggestions derive from the following facts:
Books
Links
See also |
||
|
|
|
|
|
|
Copyright 2008 WordIQ.com - Privacy Policy
::
Terms of Use
:: Contact Us
:: About Us This article is licensed under the GNU Free Documentation License. It uses material from the Wikipedia article "Work breakdown structure". |